Movement of Overburden Stratum and Damage Evolution of Floor Stratum during Coal Mining above Aquifers
Yuan RF(袁瑞甫); Li YQ; Jiao ZH
2015
会议名称New Paradigm of Particle Science and Technology Proceedings of The 7th World Congress on Particle Technology
会议日期May 19–22, 2015
会议地点Beijing, China
关键词mining above aquifer numerical simulation overburden stratum movement water inrush risk
中文摘要Based on coal mining above aquifers of Carboniferous limestone in a coal mine in North China Mining Area, the numerical method of CDEM (Continuum-based Discrete Element Method) was employed to simulate the movement of overburden stratum and damage evolution of floor stratum during coal mining above aquifers. The results indicated that the lithology, thickness, and structure of the impermeable strata and the pressure of confined water were the most pivotal elements which lead to the risk of water inrushes and damage evolution of floor stratum. In addition, the activities of overburden stratum, such as deformation, stratum separation, caving, also exhibited important effects. Compared to caving activities of the immediate roof and main roof, the critical upper strata with the larger thickness and strength showed more important influence on the damage evolution of floor stratum and water inrush risk, although it was relatively far from the coal seam. Before the initial caving of critical roof, the destruction extent of floor stratum and the risk of water inrush increased with the increase of the mined-out area and reached their peaks when the maximum caving interval was reached. When critical strata started periodic caving, the extent of destruction of floor and the risk of water inrush reached their peaks when hanging arch of critical strata reached the maximum value in this period. For caving interval in critical strata is larger than the mail roof and the stress pressure was mainly applied in the rear of the mined-out area other than the mining face, it is difficult to observe the rules of the activities of critical strata above coal seam through conventional mining monitoring ways. The activities of critical strata above coal seam should be studied to effectively prevent water inrush disaster in coal mine.
收录类别CPCI-S ; EI
会议网址http://dx.doi.org/10.1016/j.proeng.2015.01.324
语种英语
WOS记录号WOS:000383259700221
内容类型会议论文
源URL[http://dspace.imech.ac.cn/handle/311007/55289]  
专题力学研究所_流固耦合系统力学重点实验室(2012-)
推荐引用方式
GB/T 7714
Yuan RF,Li YQ,Jiao ZH. Movement of Overburden Stratum and Damage Evolution of Floor Stratum during Coal Mining above Aquifers[C]. 见:New Paradigm of Particle Science and Technology Proceedings of The 7th World Congress on Particle Technology. Beijing, China. May 19–22, 2015.http://dx.doi.org/10.1016/j.proeng.2015.01.324.