Construction techniques of pre-stressed anchor cables for the exit slope of the Majiashan tunnel
Zhu, Shiwei1; Wu, Fazhan2,3
刊名Modern Tunnelling Technology
2013-10-01
卷号50期号:5页码:164-168
关键词Anchor cables Cables Construction equipment Cost engineering Reinforcement Roads and streets Slope protection Cable construction Construction technique Engineering practices Ground surfaces Pre-stressed anchor Railway tunnels Slope reinforcement Surrounding environment
ISSN号10096582
英文摘要The exit section of the Majiashan tunnel is located in a weathered bedrock layer, with a county-level road underneath. Due to the construction of the road, an artificial steep slope of 70° and 25~30 m high was formed. To stabilize the rock mass and strengthen the ground, SNS active protection mesh and a pre-stressed anchor cable were adopted. In this paper the application of the pre-stressed anchor cable construction techniques to the portal slope reinforcement of the Majiashan tunnel are introduced, including the design, construction, equipment, quality control and safety measures, etc. The engineering practice indicates the slope reinforcement with a pre-stressed anchor cable has the advantages of small quantities of earth-work and concrete, as well as low costs and minimal landscaping. Additionally the construction of the anchor cable has less impact on the slope and the surrounding environment, assuring safe construction and obtaining reinforcement goals.
语种中文
出版者China Railway Southwest Research Institute Co. Ltd., No.97 Gunan Street, West Hi-Tech Zone, Chengdu, 611731, China
内容类型期刊论文
源URL[http://ir.lut.edu.cn/handle/2XXMBERH/113765]  
专题兰州理工大学
作者单位1.Beijing Tiecheng Construction Supervision Co. Ltd., Beijing 100855, China;
2.China Railway Tunnel Co. Ltd., Luoyang 471009, China;
3.Lanzhou University of Technology, Lanzhou 730050, China
推荐引用方式
GB/T 7714
Zhu, Shiwei,Wu, Fazhan. Construction techniques of pre-stressed anchor cables for the exit slope of the Majiashan tunnel[J]. Modern Tunnelling Technology,2013,50(5):164-168.
APA Zhu, Shiwei,&Wu, Fazhan.(2013).Construction techniques of pre-stressed anchor cables for the exit slope of the Majiashan tunnel.Modern Tunnelling Technology,50(5),164-168.
MLA Zhu, Shiwei,et al."Construction techniques of pre-stressed anchor cables for the exit slope of the Majiashan tunnel".Modern Tunnelling Technology 50.5(2013):164-168.
个性服务
查看访问统计
相关权益政策
暂无数据
收藏/分享
所有评论 (0)
暂无评论
 

除非特别说明,本系统中所有内容都受版权保护,并保留所有权利。


©版权所有 ©2017 CSpace - Powered by CSpace